30 years, two 180-day phases, filed as an RCT record.

Get Your Free Proposal

Tell us about your building and any notice or deadline you have. We will respond right away with next steps and a proposal.

Your building department decides if salt water means a 25-year inspection.

We arrange the inspection with a Florida-licensed engineer or architect and coordinate the Accela filing with your manager.

  • Free, no-obligation proposal
  • Inspections by Florida-licensed engineers and architects
  • Milestone, SIRS and recertification deadlines

The short answer

Tampa condo and co-op buildings follow City Code s. 5-110.9: a first milestone inspection at 30 years and every 10 years after, Phase 1 within 180 days of the city's notice, Phase 2 within 180 days of the Phase 1 report, and reports filed in Accela Citizen Access as an RCT record (City of Tampa).

Last updated

What the state data shows

Local building departments reported 8,736 Phase 1 and 1,575 Phase 2 inspections completed across 2024 and 2025. They received 903 Phase 2 repair permit applications, with an average permit value of $337,229 in 2024 and $496,236 in 2025.

Tampa timeline

  • Notice from the city: the 180-day Phase 1 clock starts
  • Within 14 days: association notifies owners (state law)
  • Within 180 days: Phase 1 report filed as an RCT record
  • Within 180 days of Phase 1: Phase 2 report, if Phase 2 is required
  • Within 45 days of each report: summary to owners (state law)
[1][2]

Milestone inspection rules in Tampa

Condominium towers along a bayfront boulevard with a long white balustrade beside Tampa Bay
  • Phase I must be completed within 180 days after the owners receive the city's written notice under s. 5-110.9.8.
  • Reports are filed in Accela Citizen Access, where a registered user applies for an RCT record, and each report must be performed, signed and sealed by a Florida design professional.
  • The city's program page shows the 30-year trigger only and no 25-year rule for buildings near salt water, so bayfront towers on Bayshore and Harbour Island follow the same 30-year clock as inland buildings unless the city notifies otherwise.
  • Buildings that should be in the program but have not received a notice are asked to contact CSDLSP@tampagov.net or 813-307-3980, and the city posts its Milestone Inspection Notification Letter.
  • The city's page sets inspection deadlines but no repair deadline of its own, so the state rule applies, under which repairs for substantial structural deterioration must start within 365 days of the Phase II report.
[1][2]

How we handle milestone inspections in Tampa

Tampa keeps to the statute's shape with its own filing route. The city's notice starts a 180-day Phase I clock, Phase II follows within 180 days of the Phase I report, and both are filed by a Florida design professional as an RCT record in Accela. We get the engineer registered and the record opened early, because the clock does not stop while the account is set up.[1]

Bound engineering report open to photos of cracked concrete and a balcony slab edge, with reading glasses and a highlighter

Permits for milestone inspections in Tampa

When is a milestone inspection due?

By 31 December of the year the building reaches 30 years from its certificate of occupancy, and every 10 years after that. If the certificate date is not available, the building official's records of occupancy set the date. Buildings that turned 30 before 1 July 2022 were due before 31 December 2024, and those that turned 30 between 1 July 2022 and 31 December 2024 were due before 31 December 2025.[2]

Is it 25 years within 3 miles of the coast?

Not automatically any more. The 2022 law set 25 years for buildings within 3 miles of the coastline. The 2023 law (SB 154) replaced that with a local choice, so the local enforcement agency now decides whether local circumstances, such as proximity to salt water, require 25 years. Many South Florida departments chose to keep the 3-mile line; Tampa and Pinellas use 30 years. Check your own department.[2][4][5][6][1][7]

Older twelve-storey condominium directly behind the dunes and sea grape on a barrier island beach

How do Phase 1 and Phase 2 work?

  • The building department sends written notice by certified mail, return receipt requested.
  • The association tells unit owners within 14 days, with the due date.
  • Phase 1, a visual examination and qualitative assessment, is completed within 180 days of the notice, when the architect or engineer submits the report to the building department.
  • Phase 2, with destructive or nondestructive testing, is required only if Phase 1 finds substantial structural deterioration. A progress report with a timeline is due within 180 days of the Phase 1 report.
  • The association sends the inspector's summary to every owner within 45 days of receiving a report.
  • Repairs for substantial structural deterioration must start within 365 days of the Phase 2 report.
[2]

Who performs the inspection?

An architect licensed under chapter 481 or an engineer licensed under chapter 471 who is authorized to practise in Florida. A team may do the work with an architect or engineer as the registered design professional in responsible charge, and all work and reports are signed and sealed by the qualified team member. We arrange and coordinate the inspection; the professional performs it and seals the report.[2]

Open equipment case with inspection instruments and a ground penetrating radar cart on a condominium walkway
Milestone inspections in Tampa: the local rules at a glance
TopicRule in TampaSource
First inspectionTampa requires milestone inspections under City Code s. 5-110.9 at 30 years and every 10 years after.City of Tampa
ContactTampa Construction Services takes milestone questions at (813) 274-3100, option 1.City of Tampa
NoticePhase I is due within 180 days after the owners receive the city's written notice.City of Tampa
From the official pages, read 28 October 2026. Confirm dates with the City of Tampa Construction Services. Source: City of Tampa, Condo milestone inspections, City of Tampa Construction Services. Last updated October 28, 2026.

Frequently asked questions

Does Tampa require Phase 2 to be finished in 180 days?

The city page says Phase 2 within 180 days of the Phase 1 report. State law requires a progress report with a timeline within that period. Ask the city if your Phase 2 will run longer.

Who do we contact at the city?

The city lists CSDLSP@tampagov.net for milestone inspections.

When is a milestone inspection due in Tampa?

Tampa runs milestone inspections under City Code s. 5-110.9, Mandatory Structural Inspections for Condominium and Cooperative Buildings, for association buildings three stories or more. The first inspection is due at 30 years from the certificate of occupancy and then every 10 years. The building department's notice letter is the document that fixes your date.

Does Tampa use the 25-year coastal rule?

The city's page shows a 30-year trigger and no 25-year coastal rule.

Sources

  1. Condo milestone inspections, City of Tampa Construction Services, City of Tampa. Accessed October 28, 2026.
  2. s. 553.899, Florida Statutes, Online Sunshine, Florida Legislature. Accessed October 28, 2026.
  3. Milestone Inspection Reporting Data 2024 and 2025, Report 26-04, July 2026, Florida Legislature, OPPAGA. Accessed October 27, 2026.
  4. Chapter 2022-269, Laws of Florida (SB 4-D), approved May 26 2022, Florida Department of State / Laws of Florida. Accessed October 27, 2026.
  5. Chapter 2023-203, Laws of Florida (CS/CS/SB 154), approved June 9 2023, Laws of Florida. Accessed October 27, 2026.
  6. Mandatory Milestone Inspections, Palm Beach County Building Division, Palm Beach County. Accessed October 28, 2026.
  7. Condo Milestone Inspections, Pinellas County, Pinellas County. Accessed October 28, 2026.

Get a free quote

Tell us about your project and we will get back to you fast.