Your building department decides if salt water means a 25-year inspection.

We arrange the milestone inspection with a Florida-licensed engineer or architect and line it up with your city recertification so the board deals with one schedule.

  • Free, no-obligation proposal
  • Inspections by Florida-licensed engineers and architects
  • Milestone, SIRS and recertification deadlines

The short answer

City of Miami condo and co-op buildings three habitable stories or more need a state milestone inspection at 30 years, or 25 where the local agency requires it near salt water, and they also fall under the county recertification code the city applies. Miami-Dade building officials reported 308 required Phase 2 inspections in 2025, more than any other county that reported that year (OPPAGA Report 26-04).

Last updated

What the state data shows

Local building departments reported 8,736 Phase 1 and 1,575 Phase 2 inspections completed across 2024 and 2025. They received 903 Phase 2 repair permit applications, with an average permit value of $337,229 in 2024 and $496,236 in 2025.

Milestone and recertification in one plan

Miami-Dade's recertification schedule puts coastal condo and co-op buildings built from 1998 at 25 years and other buildings built from 1993 at 30 years. The state milestone rule runs from the certificate of occupancy. Ask the engineer to scope one inspection that meets both where the city allows it, and file each report the way its program requires.[2][4]

After the report in the City of Miami

The city gives 60 days after filing a recertification report to obtain repair permits without a violation. Under state law, repairs for substantial structural deterioration found in a Phase 2 report must commence within 365 days.[3][4]

Milestone inspection rules in Miami

Brickell and downtown Miami condominium towers along Biscayne Bay
  • Buildings built in 1982, 1983 or 1984 that show as overdue cannot use the city's online process and have to contact the recertification team directly.
  • Because the city applies Miami-Dade's Code s. 8-11(f), the county's age rules decide the due year. Coastal condo and co-op buildings built from 1998 within three miles of the coast come due at 25 years, and most other buildings built from 1993 at 30.
  • In 2025 Miami-Dade accounted for 23 of the 24 buildings in Florida found unsafe or uninhabitable after milestone inspections.
  • The city says to expect a response in about six weeks, and takes questions at buildingrecertifications@miamigov.com or (305) 416-1177.
  • Across Miami-Dade, building officials counted 308 required Phase 2 milestone inspections in 2025.
  • The city allows one extension, for a $500 fee, and only if it is requested before the due date.
  • Once a report is filed, the owner has 60 days to obtain the repair permits it calls for without a violation being issued.
  • For threshold buildings, the county guidelines the city applies call for separate structural and electrical engineers, and the structural engineer shows proof of structural specialization.
[3][2][1]

How we handle milestone inspections in Miami

A City of Miami condo tower files the state milestone inspection and the county recertification through the same iBuild and ProjectDox route. Lining them up matters because the city leaves little slack, one paid extension asked for before the due date and 60 days after filing to pull repair permits, so we schedule the engineer to deliver both reports together where the city accepts it.[3][4]

Bound engineering report open to photos of cracked concrete and a balcony slab edge, with reading glasses and a highlighter

Permits for milestone inspections in Miami

When is a milestone inspection due?

By 31 December of the year the building reaches 30 years from its certificate of occupancy, and every 10 years after that. If the certificate date is not available, the building official's records of occupancy set the date. Buildings that turned 30 before 1 July 2022 were due before 31 December 2024, and those that turned 30 between 1 July 2022 and 31 December 2024 were due before 31 December 2025.[4]

Is it 25 years within 3 miles of the coast?

Not automatically any more. The 2022 law set 25 years for buildings within 3 miles of the coastline. The 2023 law (SB 154) replaced that with a local choice, so the local enforcement agency now decides whether local circumstances, such as proximity to salt water, require 25 years. Many South Florida departments chose to keep the 3-mile line; Tampa and Pinellas use 30 years. Check your own department.[4][5][6][7][8][9]

Older twelve-storey condominium directly behind the dunes and sea grape on a barrier island beach

How do Phase 1 and Phase 2 work?

  • The building department sends written notice by certified mail, return receipt requested.
  • The association tells unit owners within 14 days, with the due date.
  • Phase 1, a visual examination and qualitative assessment, is completed within 180 days of the notice, when the architect or engineer submits the report to the building department.
  • Phase 2, with destructive or nondestructive testing, is required only if Phase 1 finds substantial structural deterioration. A progress report with a timeline is due within 180 days of the Phase 1 report.
  • The association sends the inspector's summary to every owner within 45 days of receiving a report.
  • Repairs for substantial structural deterioration must start within 365 days of the Phase 2 report.
[4]

Who performs the inspection?

An architect licensed under chapter 481 or an engineer licensed under chapter 471 who is authorized to practise in Florida. A team may do the work with an architect or engineer as the registered design professional in responsible charge, and all work and reports are signed and sealed by the qualified team member. We arrange and coordinate the inspection; the professional performs it and seals the report.[4]

Open equipment case with inspection instruments and a ground penetrating radar cart on a condominium walkway
Milestone inspections in Miami: the local rules at a glance
TopicRule in MiamiSource
FilingCity of Miami reports go in through iBuild and ProjectDox under set file names such as RC-S and RC-E.City of Miami
First inspectionOverdue buildings built from 1982 to 1984 cannot use the city's online filing route.City of Miami
First inspectionUnder the county schedule the city applies, coastal condos built from 1998 are due at 25 years and most other buildings from 1993 at 30.Miami-Dade County
From the official pages, read 28 October 2026. Confirm dates with the City of Miami Building Department. Sources: Miami-Dade County, Recertification (Miami-Dade County Building); City of Miami, Get a Building Recertification (City of Miami). Last updated October 28, 2026.

Frequently asked questions

Do City of Miami condos need both a milestone inspection and recertification?

Usually yes. The state milestone law covers condo and co-op buildings three habitable stories or more, and the county recertification code the city applies covers most buildings. One well-scoped inspection can often serve both; confirm with the city.

How common is Phase 2 in Miami-Dade?

Miami-Dade reported 308 required Phase 2 milestone inspections in 2025, and 23 of the 24 buildings found unsafe or uninhabitable statewide that year.

When is a milestone inspection due in Miami?

Buildings built in 1982, 1983 or 1984 that show as overdue cannot use the city's online process and have to contact the recertification team directly. The building department's notice letter is the document that fixes your date.

Do we file with Miami-Dade County or the City of Miami?

Buildings inside City of Miami limits file with the city through iBuild and ProjectDox. The county handles unincorporated Miami-Dade.

Sources

  1. Milestone Inspection Reporting Data 2024 and 2025, Report 26-04, July 2026, Florida Legislature, OPPAGA. Accessed October 27, 2026.
  2. Recertification (Miami-Dade County Building), Miami-Dade County. Accessed October 28, 2026.
  3. Get a Building Recertification (City of Miami), City of Miami. Accessed October 27, 2026.
  4. s. 553.899, Florida Statutes, Online Sunshine, Florida Legislature. Accessed October 28, 2026.
  5. Chapter 2022-269, Laws of Florida (SB 4-D), approved May 26 2022, Florida Department of State / Laws of Florida. Accessed October 27, 2026.
  6. Chapter 2023-203, Laws of Florida (CS/CS/SB 154), approved June 9 2023, Laws of Florida. Accessed October 27, 2026.
  7. Mandatory Milestone Inspections, Palm Beach County Building Division, Palm Beach County. Accessed October 28, 2026.
  8. Condo milestone inspections, City of Tampa Construction Services, City of Tampa. Accessed October 28, 2026.
  9. Condo Milestone Inspections, Pinellas County, Pinellas County. Accessed October 28, 2026.

Get a free quote

Tell us about your project and we will get back to you fast.