Phase 2 milestone inspection in Pinellas County

Testing and a repair program when Phase 1 finds deterioration.

Get Your Free Proposal

Tell us about your building and any notice or deadline you have. We will respond right away with next steps and a proposal.

Your building department decides if salt water means a 25-year inspection.

We arrange and coordinate Phase 2 inspections for condo and co-op associations in Pinellas County, working to the rules of the Pinellas County Building and Development Review Services from the first notice to the final report.

  • Free, no-obligation proposal
  • Inspections by Florida-licensed engineers and architects
  • Milestone, SIRS and recertification deadlines

The short answer

Phase 2 adds destructive or nondestructive testing when Phase 1 finds substantial structural deterioration, and in Pinellas County it follows local filing rules as well as s. 553.899. Phase 2 testing is done at the least disruptive, most easily repaired locations. 8 Pinellas buildings were found unsafe or uninhabitable in 2024, the second highest county count.

Last updated

Who this is for

Associations whose Phase 1 report found substantial structural deterioration, and boards preparing for the cost of the repairs that usually follow.

Phase 2 repair costs in the state data

OPPAGA counted 903 Phase 2 repair permit applications for 2024 and 2025, from under $1,000 to $30 million. The average permit value was $337,229 in 2024 and $496,236 in 2025, and the most common repairs were concrete, electrical and structural.

Phase 2 in Pinellas County

High-rise condominiums on a white sand Gulf Coast beach with calm green water
  • For Phase 2, the county page notes the inspector prefers the least disruptive and most easily repaired locations for testing.
  • In the state's 2024 data, 8 Pinellas buildings were found unsafe or uninhabitable after milestone inspections, out of 30 statewide and behind only Osceola County.
  • Ordinance 24-18 sets the county process, and associations register on the Pinellas County Access Portal before reports can be filed.
  • The county says that if a building is in a Special Flood Hazard Area, the 49% rule applies to repairs, which can change the scope and cost of a large repair project.
  • The county describes Phase 1 as a visual examination of the habitable and non-habitable areas of the building by a Florida architect or engineer, who decides whether Phase 2 testing is needed.
[1][2]

How we handle Phase 2 inspections in Pinellas County

Pinellas splits the filing by jurisdiction. If your building is in unincorporated Pinellas or one of the seven towns the county serves, the report goes through the county's Access Portal after registration; if it is in St. Petersburg, Clearwater or another city, it goes to that city. We confirm the right office before the inspection, so the sealed report lands where the clock is running.[1]

Clear crack monitoring gauge screwed across a diagonal crack in a condominium stairwell wall

Permits in Pinellas County

What does Phase 2 testing involve?

The inspector decides the testing, which can be destructive, such as cores or opening up a slab edge, or nondestructive. The statute tells the inspector to prefer locations that are least disruptive and most easily repaired while still representative of the structure. Plan for unit access, noise and temporary protection.[3]

Concrete core samples, one showing a corroded rebar end, beside a cored hole and a core drill bit on a balcony slab

Phase 2 deadlines

Rebar scanner and sounding hammer on a condo balcony slab marked with chalk grid lines
  • Within 180 days of the Phase 1 report: progress report to the building department with a timeline for completing Phase 2
  • On completion: sealed Phase 2 report and summary to the association, any non-condo owner and the building official
  • Within 45 days of receiving it: summary to every owner
  • Within 365 days of the Phase 2 report: repairs for substantial structural deterioration must have commenced, or the building department must check whether the building is unsafe for occupancy
[3]
Phase 2 inspections in Pinellas County: the local rules at a glance
TopicRule in Pinellas CountySource
FilingThe county files for unincorporated Pinellas and seven towns including Indian Rocks Beach and Belleair Beach.Pinellas County
NoticeNotices arrive by certified mail, and owners must be told within 14 days.Pinellas County
ContactThe county takes milestone questions at Milestone@pinellas.gov.Pinellas County
From the official pages, read 28 October 2026. Confirm dates with the Pinellas County Building and Development Review Services. Source: Pinellas County, Condo Milestone Inspections, Pinellas County. Last updated October 28, 2026.

Frequently asked questions

What happens after a Phase 2 finding in Pinellas County?

For Phase 2, the county page notes the inspector prefers the least disruptive and most easily repaired locations for testing. The Phase 2 report also sets out the repairs the engineer recommends, which become the repair scope.

Does Pinellas County handle reports for our city?

The county files for unincorporated Pinellas and seven municipalities, Belleair Beach, Belleair Bluffs, Belleair Shore, Indian Rocks Beach, Oldsmar, Safety Harbor and Kenneth City. Other cities file with their own building departments.

Does the flood zone affect milestone repairs in Pinellas?

The county says the 49% rule applies to repairs if the building is in a Special Flood Hazard Area.

How do we register in Pinellas County?

On the Pinellas County Access Portal, following the county's registration guide for condo milestone inspections.

Sources

  1. Condo Milestone Inspections, Pinellas County, Pinellas County. Accessed October 28, 2026.
  2. Milestone Inspection Reporting Data 2024 and 2025, Report 26-04, July 2026, Florida Legislature, OPPAGA. Accessed October 27, 2026.
  3. s. 553.899, Florida Statutes, Online Sunshine, Florida Legislature. Accessed October 28, 2026.